The project is located in Antopolo, Philippines, invested by Cemex, and our company is responsible for the construction of pile foundation and slope protection.
The project started on August 11, 2019, and all pile foundation construction tasks were completed on September 5, 2020. Anchor cable construction began on July 4, 2021 and all anchor cable construction tasks were completed on November 2, 2021. A total of 920 bored piles and 336 anchor piles were completed.
All the staff of the project department worked together to resolutely implement the principle of safety first and prevention first in the construction process, strengthen safety management, actively implement the company's epidemic prevention measures, no safety accidents occurred during the implementation of the project, and the test results of the pile foundation and anchor cable were all qualified. The construction task was successfully completed, which was unanimously praised by the owner unit and the general contractor.