This project is located in Huizhou City, Guangdong Province, invested by CNOOC Huizhou Petrochemical Co., Ltd, and our company was responsible for the pile foundation construction of this project.
The project started on March 2, 2022 and was completed on May 3, 2022, with a total of more than 260 piles completed, and the actual construction period met the contract requirements. After the completion of the project, the owner commissioned a third-party pile foundation testing company to carry out testing. Through high strain test, acoustic transmission method and low strain test, all pile foundations were qualified and met the contract quality requirements.
In order to ensure the construction progress, the project department actively organized and coordinated, reasonably arranged the layout of drilling rigs and piling order, to ensure that each rig could be utilized to its fullest extent. During the construction period, the project department experienced the hot weather of rain in the early stage and rising temperature in the late stage, the project department played the spirit of iron army and successfully completed the pile foundation construction work despite the difficulties.