The is located in Gwadar City, Balochistan Province, southwest of Pakistan, and the representative of the Chinese owner is the Agency for International Economic Cooperation, Ministry of Commerce of PRC, and the representative of the Pakistani owner is the Pakistan Civil Aviation Authority. Our company undertakes the pile foundation construction of this project, and has completed a total of 743 bored piles with a diameter of 600 mm, 64 bored piles with a diameter of 800 mm, and the concrete grade is C40P8.
The construction of the test pile started on February 21, 2021 and was completed on February 25, 2021. The engineering pile was officially started on May 20 and completed on September 23, 2021.
In the construction process, our project department strictly implemented the relevant standard requirements of the owner and the company, strictly organized, scientifically managed, fully accepted the management and supervision of the owner, the supervising engineer and the relevant departments, and self-inspected and re-inspected the quality, progress and safety of the project, and eliminated the flow of unqualified products to the next process. The qualification rate of the pile foundation test is 100%, meeting the requirements of the bidding documents and contracts, and meeting the quality standards of the specified acceptance specifications.
During the construction process of this project, the construction process of this project is aimed at "zero" accidents in occupational health and safety and environmental, we strictly managed and carefully constructed. Therefore, the quality, safety and progress management have been praised by the technical team and management team.